ISO 9001 AND ISO 3834 CERTIFICATES

Completed investments

Water boiler plant in Ścinawka Średnia, near Kłodzko

REALIZED IN 2008

As factory expansion plans were not realized and, therefore, heat energy demand was too low, WR 2.5-0.35 coal-fired boilers (with a total nominal capacity of 8,55 MW) were turned off.
We installed two high-temperature boilers (LOOS International), which provide the constant parameter of 140/70 °C.They are based on flame tube and smoke tube technology, automatized and equipped with measurement, control, and safety system. Return flow temperature safeguard with a boiler circuit pump and three-way control valve was also installed.
There is also a pump system, which is automatically switched in case of emergency, as well as temporarily. It is controlled by a power inverter.
Pressure stabilization and water filling is provided by stabilizing and make-up pumps system, as well as shut-off valve, compatible with treated water storage.
As the boiler plant is fully automatized, it is possible to monitor the work of each module to find out and correct mistakes.

Investor:
ZETKAMA Spółka Akcyjna
ul. 3 Maja 12
PL 57-410 Ścinawka Średnia
www.zetkama.com.pl

 

Address

ul. Towarowa 15, 58-100 Świdnica

(+48) 74 856 81 88

best@systemy-grzewcze.pl

Mon-Fri: 7am-3pm

Shortcuts

 

©2019 BEST Systemy-Grzewcze. All rights reserved. Design: Art Open Studio Reklamy