REALIZED IN 2003
The steam boiler plant, with a capacity of 3 200 kg/h, a pressure of 10 bar, GZ-50 natural gas-fired, for BOMILLA Company. Feed water tank was installed on a support structure (3,5 m above the floor level) in a boiler room.
The process steam is being transferred to production lines, heating system, and hot water production system.
The scope of work: materials delivery (apart from steam boiler) and machines installation.